Work Plan

In the project we are dealing with 26 activities that can be seen in the following table:

#  Activities Team Responsible 
1 Kick-off meeting. Each meeting will have a preparation phase before it and an evaluation phase after. The first meeting will set up the final planning of the project concerning activities, dates and meetings

FS22

Participants: ALL

2 On-line collaborative tools. Report with the procedures the project will have concerning all the online communication, as it is very important to be sure that we keep the momentum during all the project and not only during meetings

FS22

Participants: ALL

3 State of Art Report. The report will compile a basic gathering of existing educational repositories and their way of working. And if possible get the taxonomy they are using

SZÁMALK

Participants: ALL

Compose first version of taxonomy

YIMEM

Participants: ALL

5 Creation and sending of 1st eNewsletter.

OAKE

Participants: ALL

6 Develop the Web site (Information part)

FS22

Participants: ALL

Design the questionnaire for VET teachers.

ATEML

Participants: ALL

8 2nd Project Meeting

YIMEM (TR)

Participants: ALL

9 Develop the questionnaire on-line

AGT

Participants: ALL

10 Deployment of questionnaires

ATEML

Participants: ALL

11 Creation of Taxonomy Report

ATEML

Participants: ALL

12 3rd Project Meeting 

SZÁMALK (HU)

Participants: ALL

13 Creation and sending of 2nd eNewsletter

ATEML & YIMEM

Participants: ALL

14 Interim Report as National Agency requirement 

 FS22

Participants: ALL

15 Creation of Web Site Repository and eLearning Platform (working with the taxonomy developed in output 11)

FS22

Participants: ALL

16 4th Project Meeting 

OAKE (UK)

Participants: ALL

17 Design and realisation of seminars to teachers about the use of the repository and pedagogical methodologies to promote creativity, collaboration and entrepreneurship.

 FS22 (ON-LINE)

SZÁMALK (PRESENCE)

Participants: ALL

18 Pilot of the repository

 YIMEM

Participants: ALL

19 Creation and sending of 3rd eNewsletter

 SZÁMALK

Participants: ALL

20 5th Project Meeting

ATEML (TR)

Participants: ALL

21 Final version of Web Site Repository

FS22

Participants: ALL

22 4th Newsletter

 AGT

Participants: ALL

23

Final Project Meeting

AGT (ES)

Participants: ALL

24 Copyrights and data protection recommendations

AGT

Participants: ALL

25 Evaluation Report

OAKE

Participants: ALL

26 Final Report. National Evaluation Report Agency requirement

FS22

Participants: ALL